July 30, 2008

New Soil Sets Foundation for Landscaping

This Week's Construction Update

A whirlwind of activity resumed at the site last week following the resolution of the drivers' strike hampering construction deliveries across the City. Concrete was poured to finalize the west playground retaining wall, and new granite curbs were installed along the northern edge of the site. The curbs are a first step toward completion of the underground tree insulation wall, sidewalk and tree pits intended to line 17th Street. Efforts to excavate, clean and underpin the pavilion structure to support the basement offices also continued.

Now that the retaining walls have begun to take shape, the full extent of the expanded playground is clearly evident. Delivery of soil last week further delineated the playground and now gives a sense of where landscaped areas will teem with beautiful new plant life.

This week, soil will be delivered to backfill the tree pit trench along 17th Street, and lighting conduits will be installed along the length of the northern perimeter. Once this work is done, the temporary pedestrian walkway will be relocated from the center of the site to its northern edge. Pavement removal will then commence, clearing the way to begin installation of the plaza's site drainage system.

Question of the Week

Question:  Why are different soil types necessary to sustain project landscaping?

Answer:  Soil content and layering for the North End Project has been engineered to maximize the lifespan of trees and shrubs given the site's dense urban context.  The deepest soil layer consists of six inches of porous sand spread over the landscape underdrain structure.  The middle planting layer, where the bulk of root systems will be located, will consist of a mix of soil and sand that will prevent soil from compacting and thereby facilitate healthy root growth.  The top layer will consist of approximately six to twelve inches of organically rich soil that will percolate down through the tree root systems and provide them with valuable nutrients.  Each autumn, when leaves fall to the tree pits and playground, organic matter will again replenish the topsoil on an annual basis.  

Photos


(Above) Aerial photo of the construction site shows 11% completion of the project to date. (Below) Crews continue to fill the tree insulation pit with new soil.

Information
To report a problem in the park, call 311.
 
To report a construction or any other kind of emergency, call 911.
 
To download a PDF copy of the North End Project brochure, click here.
Greenmarket

The Union Square Greenmarket is fully operational and accommodated on site throughout construction so stop during their regularly scheduled hours of operation Monday, Wednesday, Friday and Saturday from 8:00 AM to 6:00 PM to pick up some of this season’s bounty.



Union Square Partnership
4 Irving Place Room 1148-S
New York, NY 10003 - US
%%!account_telephone%%
Forward to a Friend
Unsubscribe

Email marketing delivered by Bronto