|
|
|
Excavation
at the Site to Be Short-Lived |
| |
|
|
|
This Week's
Construction Update
Padilla
Construction Services (PCS), the general
contractor, began excavating rock from
beneath the former east playground in order both
to expand the play area and to create space for
public restroom facilities in that
location. The rock excavation is slated
to last only through the end of this week, when
the site should be fully excavated. Future
work that may require some jack
hammering or other loud activity includes utility
trenching, and demolition of the Pavilion's
concrete floor. The latter
is necessary in order to stabilize and
restore the structural foundation of the
building. This work should also be
completed within the next 1 - 2
weeks.
In addition to excavation and
demolition work, PCS has salvaged much of the
existing building materials for reuse once the
Pavilion has been refurbished and playground
expanded. The clay roof tiles, original
to the building, are being saved for reuse, as are
the granite stones from the retaining
wall. When the work is complete, the stone
will once again encircle and protect the
playground, as well as form part of the façade
material for the new public restroom
building. Other site work completed this week
includes pouring the concrete tree insulation
wall, backfilling the tree pit trench with soil,
and beginning installation of the site's storm
drainage system. New Feature:
Question of the
Week
Question: "I heard that
the [North End] project includes adding two new
lanes of traffic along 17th
Street, is this true?"
- 15th
Street Resident
Answer:
No. In fact, prior to the finalization of the
North End construction plans, the Parks Department
and the Union Square
Partnership asked the Department of
Transportation (DOT) to conduct a study
to determine if we could eliminate roadway to
give back to the park. The DOT study
found that we could transfer 5 feet from the
roadway to the plaza along the entire stretch
of 17th Street, which will
increase plaza space. Additionally, plans
include the removal of all Muni-meter parking
along the west side of the park, which will create
even more park land space for pedestrian and
Greenmarket use. When work on the north plaza
is complete, there will be no reduction of plaza
space for the Greenmarket and they will return to
the north end.
Please submit
project-related questions to
info@unionsquarenyc.org and we will seek to answer
them in future email updates. For more
information about the project, visit unionsquarenyc.org/northend. | | | |
|
|
|
|
|
|
|
|

(Above) Excavation of the
rock bed under the former east playground should
be over by the end of this week. (Below)
Sections of the granite retaining wall are
being salvaged for future reuse at the
site.

|
| |
|
|
|
|
|
|
|
|
|
To report a problem in the
park, call 311.
To report a construction or
any other kind of emergency, call
911.
To download a PDF copy of the
North End Project brochure, click here. |
| |
|
|
|
|
|
|
|
|
|
The Union Square Greenmarket is
fully operational and accommodated on site throughout
construction so stop during their regularly scheduled
hours of operation Monday, Wednesday, Friday and
Saturday from 8:00 AM to 6:00 PM to pick up some of this
season’s bounty. |
| |
|
| |
|