Pavilion Structural Work Moving Quickly
This Week's Construction Update

Recent construction updates have detailed the rapid development of the plaza and playground areas, but work has also been progressing on pace for the Pavilion's interior renovation as well.  After demolition of the Pavilion floor slab last month, crews have been hard at work shoring up the exterior walls and creating the underslab column support necessary to rebuild the building's floor. 

The basement has now been stripped of all previously existing walls and utility systems in preparation for reuse as Parks Department maintenance offices.  Next week, the concrete floor slab will be poured over plywood and rebar forms inside the Pavilion, clearing the way to begin surface renovation of the building's interior.

Over the next two weeks, work will continue on the main sewer connection beneath 17th Street, and traffic will be shifted within the streetbed accordingly until the connection is complete.  Now that rock anchors have been installed in the bedrock to the east of the Pavilion beneath the future restroom facility, installation of the underslab drainage system will begin.  Work will also progress at the site's northwest corner, where new granite curb and pavers will be installed on the plaza.
 



Question of the Week

Question:  Will the Holiday Market return to Union Square this year given the state of construction?
 
Answer:  Yes, the Union Square Holiday Market and Greenmarket will coexist in the park during the holiday season as they have for the past 13 years.  The Holiday Market, operated by Urban Space Management, will be open from November 28th through December 24th. The unique and festive shopping experience offers a diverse array of fine art, antique prints, handcrafted jewelry and clothing, holiday ornaments, toys for kids of all ages, and so much more.
 
Holiday Market Hours
Monday – Friday:  11:00 AM to 8:00 PM
Saturdays:  10:00 AM to 8:00 PM
Sundays:  11:00 AM to 7:00 PM
Christmas Eve:  10:00 AM to 4:00 PM
Photos


(Above) View of the Pavilion's interior showing plywood that will form the building's new floor. 
(Below) Resident Engineer Fides Gardiner inspects a structural shoring column in the Pavilion's basement.  
 
 
Information
To report a problem in the park, call 311.
 
To report a construction or any other kind of emergency, call 911.
 
To download a PDF copy of the North End Project brochure, click here.


Union Square Partnership
4 Irving Place Room 1148-S
New York, NY 10003 - US

Forward to a Friend
Unsubscribe

Email marketing delivered by Bronto